2.A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:?
A can do work in 16 days A's 1 day work is 1/16 B can do work in 12 days B's 1 day work in 1/12 | ||||||||||||||||||||